| Maximum Reasonable Costs - Drilling
Article 4, Part 2
4-2-1. RATES PER FOOT. The following per-foot costs include all materials,
equipment, and non-consultant labor necessary to drill a boring for either a 2" or
4" diameter well. The rates shown for rotary drilling apply to either air or fluid
rotary drilling. The costs include decontamination, collecting split spoon samples in
liners at 5' intervals, and backfilling borings with bentonite grout. The costs do not
include miscellaneous small items (see Miscellaneous Field Supplies).
| Drilling
for a 2" monitoring well |
|
Drilling
for a 4" monitoring well |
| Auger |
0 - 50' |
$15.00/ft |
|
Auger |
0 - 50' |
$17.50/ft |
| Auger |
>50' |
$16.83/ft |
|
Auger |
>50' |
$19.50/ft |
| Rotary |
0 - 50' |
$19.25/ft |
|
Rotary |
0 - 50' |
$25.00/ft |
| Rotary |
>50' |
$21.50/ft |
|
Rotary |
>50' |
$27.50/ft |
4-2-2. MOBILIZATION/DEMOBILIZATION
$2.77/mile
4-2-3. SOIL SAMPLING (split spoon)
$15.63/sample. This includes decontamination, labor, materials, and equipment. This cost
is reimbursable only when samples are necessary more frequently than the 5' intervals
included in the per-foot drilling rate. Examples of when more frequent samples may be
necessary, such as when drilling the first boring and trying to locate the contamination
zone or the water level, or when there is a high fluctuation in groundwater level. No
additional consultant fees will be reimbursed. Unless OIS requires or pre-approves a soil
sampling method other than split spoon, the Fund will not reimburse additional costs for a
more expensive soil sampling method.
4-2-4. COMPLETION OF BOREHOLE AS MONITORING WELL
2" well: $13.84/ft
4" well: $19.81/ft
These rates include all associated labor and materials
4-2-5. WELL ABANDONMENT (closure)
2" well: $6.83/ft
4" well: $10.13/ft
These rates include all associated labor and materials.
4-2-48. MARKUP
No markup is permitted if the consultant does his own drilling, using his own equipment
and labor.
4-2-49. CONSULTANT LABOR AND FIELD INSTRUMENTATION Consultant on-site labor
allowable for the duration of the drilling time, plus two hours. Field instruments such as
PIDs (photo-ionization detectors) may be billed separately.
4-2-50. MISCELLANEOUS FIELD SUPPLIES
$20/day/site. This includes such items as gloves, baggies, ice, water, rope, pens, etc. No
receipts are required.
|