| Maximum Reasonable Costs - Direct Push Technology
Article 4, Part 1
4-1-1. MINIMUM AND MAXIMUM REIMBURSEMENT PER DAY
Minimum reimbursement: $700/day, plus mileage @ 90¢/mile
Maximum reimbursement: The greater of $700/day or $8/foot, not to exceed
$1,300/day, plus mileage @ 90¢/mile
These rates include mobilization, demobilization, rig up, rig down, decontamination,
and all non-consultant labor.
4-1-2. INSTALL TEMPORARY WELL IN DIRECT PUSH BORING
$20.00/well (includes all materials)
4-1-3. INSTALL PERMANENT WELL IN DIRECT PUSH BORING
$7.00/ft. The $7/ft rate includes all materials except locks and permits. Locks and
permits should be billed separately at cost plus applicable markup.
Permanent well means: 1" inside diameter casing, capable of accepting 3/4"
diameter bailer, pre-slotted screen, adequate filter pack, bentonite seal, locking cap,
street box with traffic-rated cover.
4-1-4. WELL ABANDONMENT (closure)
$40.00/well (includes materials and labor)
4-1-49. CONSULTANT LABOR AND FIELD INSTRUMENTATION
Consultant on-site labor allowable for the duration of the direct push boring time, plus
two hours.Field instruments such as PIDs (photo-ionization detectors) may be billed
separately.
4-1-50. MISCELLANEOUS FIELD SUPPLIES
$20/day/site. This includes such items as gloves, baggies, ice, water, rope, pens, etc. No
receipts are required. |