4-1-1. MINIMUM AND MAXIMUM REIMBURSEMENT PER DAY
Minimum reimbursement:    $700/day, plus mileage @  90¢/mile

Maximum reimbursement:    The greater of $700/day or $8/foot, not to exceed $1,300/day, plus mileage @ 90¢/mile

These rates include mobilization, demobilization, rig up, rig down, decontamination, and all non-consultant labor.

4-1-2. INSTALL TEMPORARY WELL IN DIRECT PUSH BORING
$20.00/well (includes all materials)

4-1-3. INSTALL PERMANENT WELL IN DIRECT PUSH BORING
$7.00/ft. The $7/ft rate includes all materials except locks and permits. Locks and permits should be billed separately at cost plus applicable markup.

Permanent well means: 1" inside diameter casing, capable of accepting 3/4" diameter bailer, pre-slotted screen, adequate filter pack, bentonite seal, locking cap, street box with traffic-rated cover.

4-1-4. WELL ABANDONMENT (closure)
$40.00/well (includes materials and labor)

4-1-49. CONSULTANT LABOR AND FIELD INSTRUMENTATION
Consultant on-site labor allowable for the duration of the direct push boring time, plus two hours.Field instruments such as PIDs (photo-ionization detectors) may be billed separately.

4-1-50. MISCELLANEOUS FIELD SUPPLIES
$20/day/site. This includes such items as gloves, baggies, ice, water, rope, pens, etc. No receipts are required.